Project Description


Large-scale reconstruction and restoration works of the existing musical center building were carried out. Whole layout of the building was completely changed.

Load-bearing frame of core and superstructure were arranged with monolithic reinforced concrete elements. Structural elements of existing load-bearing monolithic reinforced concrete frame were either strengthened or replaced. Facade and arched ceiling of the attached part were cladded with glass panels made of aluminum profiles and glazed with double-pane insulated windows. Silver-colored metal spires were installed on the walls of the building parapet. Walls and ceilings painted with decorative ornaments were completely restored. Cornices and decorative figures were renewed.

Chairs in audience space were replaced. Internal and external fountains were arranged. Full repair works were executed in interior and inner rooms. External and internal engineering networks were installed with their equipment. Scenic machinery was installed. Outer territory was paved with decorative concrete tiles, kerbs and landscaping were arranged.