Project

Ford Center, Tbilisi

Completed

Client:GT Motors LTD

Start date:Aug 2014
Completion date:Feb 2015
Total Area: 4200 m2

Project Description


According to its framed structural diagram the building represents complex of the monolithic reinforced concrete structures and factory-manufactured assembled metal structure, the so called Kislovodsk. Reinforced concrete structural frame of the building are arranged from platelike and bar elements. Façade walls are cladded with Alucobond panel façade system. External territory is covered with concrete tiles, kerbs were arranged.

Foundations – monolithic reinforced concrete pad foundations bonded with foundation beams.
Walls – small concrete masonry blocks, metal sandwich panels.
Doors, windows and glass panels – aluminum profiles, double-pane insulated windows.